We study the Multiple Cluster Scheduling problem and the Multiple Strip Packing problem. For both problems, there is no algorithm with approximation ratio better than $2$ unless $P = NP$. In this paper, we present an algorithm with approximation ratio $2$ and running time $O(n)$ for both problems. While a $2$ approximation was known before, the running time of the algorithm is at least $Ω(n^{256})$ in the worst case. Therefore, an $O(n)$ algorithm is surprising and the best possible. We archive this result by calling an AEPTAS with approximation guarantee $(1+\varepsilon)OPT +p_{\max}$ and running time of the form $O(n\log(1/\varepsilon)+ f(1/\varepsilon))$ with a constant $\varepsilon$ to schedule the jobs on a single cluster. This schedule is then distributed on the $N$ clusters in $O(n)$. Moreover, this distribution technique can be applied to any variant of of Multi Cluster Scheduling for which there exists an AEPTAS with additive term $p_{\max}$.
While the above result is strong from a theoretical point of view, it might not be very practical due to a large hidden constant caused by calling an AEPTAS with a constant $\varepsilon \geq 1/8$ as subroutine. Nevertheless, we point out that the general approach of finding first a schedule on one cluster and then distributing it onto the other clusters might come in handy in practical approaches. We demonstrate this by presenting a practical algorithm with running time $O(n\log(n))$, with out hidden constants, that is a $9/4$-approximation for one third of all possible instances, i.e, all instances where the number of clusters is dividable by $3$, and has an approximation ratio of at most $2.3$ for all instances with at least $9$ clusters.
We study the well-known two-dimensional strip packing problem. Given is a set of rectangular axis-parallel items and a strip of width $W$ with infinite height. The objective is to find a packing of these items into the strip, which minimizes the packing height. Lately, it has been shown that the lower bound of $3/2$ of the absolute approximation ratio can be beaten when we allow a pseudo-polynomial running-time of type $(n W)^{f(1/\varepsilon)}$. If $W$ is polynomially bounded by the number of items, this is a polynomial running-time. We present a pseudo-polynomial algorithm with approximation…
We consider the relaxed online strip packing problem: Rectangular items arrive online and have to be packed without rotations into a strip of fixed width such that the packing height is minimized. Thereby, repacking of previously packed items is allowed. The amount of repacking is measured by the migration factor, defined as the total size of repacked items divided by the size of the arriving item. First, we show that no algorithm with constant migration factor can produce solutions with asymptotic ratio better than 4/3. Against this background, we allow amortized migration, i.e. to save migra…
In the Demand Strip Packing problem (DSP), we are given a time interval and a collection of tasks, each characterized by a processing time and a demand for a given resource (such as electricity, computational power, etc.). A feasible solution consists of a schedule of the tasks within the mentioned time interval. Our goal is to minimize the peak resource consumption, i.e. the maximum total demand of tasks executed at any point in time. It is known that DSP is NP-hard to approximate below a factor 3/2, and standard techniques for related problems imply a (polynomial-time) 2-approximation. Our m…
This paper is motivated by periodic data transmission in autonomous cars. We considered periodic tasks (with different periods) on one or several machines. After reviewing the literature on the subject, we managed to generalize a result of Lukasiewicz et al. (i.e., the equivalence of periodic scheduling with the power of two periods and special 2D bin packing) to harmonic periods. Furthermore, we use quite old results by Coffman, Garey, and Johnson to get an approximation algorithm.
In the Strip Packing problem (SP), we are given a vertical half-strip $[0,W]\times[0,\infty)$ and a set of $n$ axis-aligned rectangles of width at most $W$. The goal is to find a non-overlapping packing of all rectangles into the strip such that the height of the packing is minimized. A well-studied and frequently used practical constraint is to allow only those packings that are guillotine separable, i.e., every rectangle in the packing can be obtained by recursively applying a sequence of edge-to-edge axis-parallel cuts (guillotine cuts) that do not intersect any item of the solution. In thi…
The recently introduced online Minimum Peak Appointment Scheduling (MPAS) problem is a variant of the online bin-packing problem that allows for deferred decision making. Specifically, it allows for the problem to be split into an online phase where a stream of appointment requests arrive requiring a scheduled time, followed by an offline phase where those appointments are scheduled into rooms. Similar to the bin-packing problem, the aim is to use the minimum number of rooms in the final configuration. This model more accurately captures scheduling appointments than bin packing. For example, a…
We study Nonpreemptive Peak Demand Minimization (NPDM) problem, where we are given a set of jobs, specified by their processing times and energy requirements. The goal is to schedule all jobs within a fixed time period such that the peak load (the maximum total energy requirement at any time) is minimized. This problem has recently received significant attention due to its relevance in smart-grids. Theoretically, the problem is related to the classical strip packing problem (SP). In SP, a given set of axis-aligned rectangles must be packed into a fixed-width strip, such that the height of the …
We study the strip packing problem, a classical packing problem which generalizes both bin packing and makespan minimization. Here we are given a set of axis-parallel rectangles in the two-dimensional plane and the goal is to pack them in a vertical strip of a fixed width such that the height of the obtained packing is minimized. The packing must be non-overlapping and the rectangles cannot be rotated. A reduction from the partition problem shows that no approximation better than 3/2 is possible for strip packing in polynomial time (assuming P$\neq$NP). Nadiradze and Wiese [SODA16] overcame th…
We introduce and study a general scheduling problem that we term the Packing Scheduling problem. In this problem, jobs can have different arrival times and sizes; a scheduler can process job $j$ at rate $x_j$, subject to arbitrary packing constraints over the set of rates ($\vec{x}$) of the outstanding jobs. The PSP framework captures a variety of scheduling problems, including the classical problems of unrelated machines scheduling, broadcast scheduling, and scheduling jobs of different parallelizability. It also captures scheduling constraints arising in diverse modern environments ranging f…
In the Two-Bar Charts Packing Problem (2-BCPP), it is required to pack the bar charts (BCs) consisting of two bars into the horizontal unit-height strip of minimal length. The bars may move vertically within the strip, but it is forbidden to change the order and separate the chart's bars. Recently, for this new problem, which is a generalization of the Bin Packing Problem (BPP), Strip Packing Problem (SPP), and 2-Dimensional Vector Packing Problem (2-DVPP), several approximation algorithms with guaranteed estimates were proposed. However, after a preliminary analysis of the solutions construct…
Multidimensional packing problems generalize the classical packing problems such as Bin Packing, Multiprocessor Scheduling by allowing the jobs to be $d$-dimensional vectors. While the approximability of the scalar problems is well understood, there has been a significant gap between the approximation algorithms and the hardness results for the multidimensional variants. In this paper, we close this gap by giving almost tight hardness results for these problems. 1. We show that Vector Bin Packing has no polynomial time $Ω( \log d)$ factor asymptotic approximation algorithm when $d$ is a large …
Motivated by modern parallel computing applications, we consider the problem of scheduling parallel-task jobs with heterogeneous resource requirements in a cluster of machines. Each job consists of a set of tasks that can be processed in parallel, however, the job is considered completed only when all its tasks finish their processing, which we refer to as "synchronization" constraint. Further, assignment of tasks to machines is subject to "placement" constraints, i.e., each task can be processed only on a subset of machines, and processing times can also be machine dependent. Once a task is s…
The following online bin packing problem is considered: Items with integer sizes are given and variable sized bins arrive online. A bin must be used if there is still an item remaining which fits in it when the bin arrives. The goal is to minimize the total size of all the bins used. Previously, a lower bound of 5/4 on the competitive ratio of this problem was achieved using jobs of size S and 2S-1. For these item sizes and maximum bin size 4S-3, we obtain asymptotically matching upper and lower bounds, which vary depending on the ratio of the number of small jobs to the number of large jobs.
We consider the bin packing problem with d different item sizes s_i and item multiplicities a_i, where all numbers are given in binary encoding. This problem formulation is also known as the 1-dimensional cutting stock problem. In this work, we provide an algorithm which, for constant d, solves bin packing in polynomial time. This was an open problem for all d >= 3. In fact, for constant d our algorithm solves the following problem in polynomial time: given two d-dimensional polytopes P and Q, find the smallest number of integer points in P whose sum lies in Q. Our approach also applies to hig…
We consider a Two-Bar Charts Packing Problem (2-BCPP), in which it is necessary to pack two-bar charts (2-BCs) in a unit-height strip of minimum length. The problem is a generalization of the Bin Packing Problem (BPP). Earlier, we proposed an $O(n^2)$-time algorithm that constructs the packing which length at most $2\cdot OPT+1$, where $OPT$ is the minimum length of the packing of $n$ 2-BCs. In this paper, we propose an $O(n^4)$-time 3/2-approximate algorithm when each BC has at least one bar greater than 1/2.
Faster Exponential Algorithms for Multi-Machine Scheduling Problems
Max Planck Institute for Informatics(马克斯·普朗克计算机科学研究所);Saarland University(萨尔兰大学);ETH, Zurich(苏黎世联邦理工学院);CISPA Helmholtz Center for Information Security(CISPA 赫尔姆霍兹信息安全中心)
We study the d-dimensional hypercube knapsack problem where we are given a set of d-dimensional hypercubes with associated profits, and a knapsack which is a unit d-dimensional hypercube. The goal is to find an axis-aligned non-overlapping packing of a subset of hypercubes such that the profit of the packed hypercubes is maximized. For this problem, Harren (ICALP'06) gave an algorithm with an approximation ratio of (1+1/2^d+epsilon). For d=2, Jansen and Solis-Oba (IPCO'08) showed that the problem admits a polynomial-time approximation scheme (PTAS); Heydrich and Wiese (SODA'17) further improve…
Online algorithms that allow a small amount of migration or recourse have been intensively studied in the last years. They are essential in the design of competitive algorithms for dynamic problems, where objects can also depart from the instance. In this work, we give a general framework to obtain so called robust online algorithms for these dynamic problems: these online algorithm achieve an asymptotic competitive ratio of $γ+ε$ with migration $O(1/ε)$, where $γ$ is the best known offline asymptotic approximation ratio. In order to use our framework, one only needs to construct a suitable on…
We study the generalized multidimensional bin packing problem (GVBP) that generalizes both geometric packing and vector packing. Here, we are given $n$ rectangular items where the $i^{\textrm{th}}$ item has width $w(i)$, height $h(i)$, and $d$ nonnegative weights $v_1(i), v_2(i), \ldots, v_{d}(i)$. Our goal is to get an axis-parallel non-overlapping packing of the items into square bins so that for all $j \in [d]$, the sum of the $j^{\textrm{th}}$ weight of items in each bin is at most 1. This is a natural problem arising in logistics, resource allocation, and scheduling. Despite being well st…
We prove new lower bounds for suitable competitive ratio measures of two relaxed online packing problems: online removable multiple knapsack, and a recently introduced online minimum peak appointment scheduling problem. The high level objective in both problems is to pack arriving items of sizes at most 1 into bins of capacity 1 as efficiently as possible, but the exact formalizations differ. In the appointment scheduling problem, every item has to be assigned to a position, which can be seen as a time interval during a workday of length 1. That is, items are not assigned to bins, but only onc…
University Paris-Saclay(巴黎萨克雷大学);Sorbonne University(巴黎索邦大学);IBISC(IBISC(需注意:IBISC是巴黎萨克雷大学下属研究机构,此处按原文提取));CNRS(法国国家科学研究中心);LIP6(LIP6(巴黎索邦大学下属实验室,此处按原文提取))
The domain of online algorithms with predictions has been extensively studied for different applications such as scheduling, caching (paging), clustering, ski rental, etc. Recently, Bamas et al., aiming for an unified method, have provided a primal-dual framework for linear covering problems. They extended the online primal-dual method by incorporating predictions in order to achieve a performance beyond the worst-case case analysis. In this paper, we consider this research line and present a framework to design algorithms with predictions for non-linear packing problems. We illustrate the app…
In rectangle packing problems we are given the task of placing axis-aligned rectangles in a given plane region, so that they do not overlap with each other. In Maximum Weight Independent Set of Rectangles (MWISR), their position is given and we can only select which rectangles to choose, while trying to maximize their total weight. In Strip Packing (SP), we have to pack all the given rectangles in a rectangular region of fixed width, while minimizing its height. In 2-Dimensional Geometric Knapsack (2DGK), the target region is a square of a given size, and our goal is to select and pack a subse…
We consider a Bar Charts Packing Problem (BCPP), in which it is necessary to pack bar charts (BCs) in a strip of minimum length. The problem is, on the one hand, a generalization of the Bin Packing Problem (BPP), and, on the other hand, a particular case of the Project Scheduling Problem with multidisciplinary jobs and one limited non-accumulative resource. Earlier, we proposed a polynomial algorithm that constructs the optimal package for a given order of non-increasing BCs. This result generalizes a similar result for BPP. For Two-Bar Charts Packing Problem (2-BCPP), when each BC consists of…
Integer linear programs of configurations, or configuration IPs, are a classical tool in the design of algorithms for scheduling and packing problems, where a set of items has to be placed in multiple target locations. Herein a configuration describes a possible placement on one of the target locations, and the IP is used to chose suitable configurations covering the items. We give an augmented IP formulation, which we call the module configuration IP. It can be described within the framework of n-fold integer programming and therefore be solved efficiently. As an application, we consider sche…
In real-time systems, in addition to the functional correctness recurrent tasks must fulfill timing constraints to ensure the correct behavior of the system. Partitioned scheduling is widely used in real-time systems, i.e., the tasks are statically assigned onto processors while ensuring that all timing constraints are met. The decision version of the problem, which is to check whether the deadline constraints of tasks can be satisfied on a given number of identical processors, has been known ${\cal NP}$-complete in the strong sense. Several studies on this problem are based on approximations …