基于运行规划的高可再生能源渗透率电网中储能选址与定容

Operations-Based Planning for Placement and Sizing of Energy Storage in a Grid With a High Penetration of Renewables

Department of Computer Science Engineering University of Washington(华盛顿大学计算机科学与工程系);Material Physics Applications Division and Center for Nonlinear Studies Theoretical Division LANL, Los Alamos, NM 87545, USA(洛斯阿拉莫斯国家实验室材料物理应用部门与非线性研究理论中心)

Krishnamurthy Dvijotham, Scott Backhaus, Misha Chertkov

AI总结:

针对高可再生能源渗透率电网,提出一种基于最优储能控制算法的启发式方法,通过分阶段限制储能节点数量和总容量,实现储能的最优选址与定容,以最小化可再生能源集成成本。

摘要:

随着输电网规模的时间间歇性可再生能源发电资源渗透率提高,灵活资源的控制对于缓解这些新能源资源带来的波动将变得重要。灵活资源可能包括新的或现有的同步发电机以及新的储能设备。如果需要增加储能,应以最优方式进行,以最小化可再生能源的集成成本,然而,储能的最优选址和定容是一个困难的优化问题。此类结果的保真度可能存在问题,因为最优规划程序通常不考虑运行和控制的时间动态效应。这里,我们使用一种最优储能控制算法来开发一种用于储能选址和定容的启发式程序。我们生成许多间歇性发电时间曲线的实例,并允许控制算法在所有节点访问无限量的储能(包括能量和功率)。基于每个节点储能的活跃度,我们在一个分阶段程序中限制储能节点的数量,寻求能够仍然缓解可再生能源波动对网络约束影响的最小储能节点数量和总网络储能。通过将我们的结果与看似“直观”的储能选址进行比较,探讨了该启发式方法的质量。

英文摘要:

As the penetration level of transmission-scale time-intermittent renewable generation resources increases, control of flexible resources will become important to mitigating the fluctuations due to these new renewable resources. Flexible resources may include new or existing synchronous generators as well as new energy storage devices. The addition of energy storage, if needed, should be done optimally to minimize the integration cost of renewable resources, however, optimal placement and sizing of energy storage is a difficult optimization problem. The fidelity of such results may be questionable because optimal planning procedures typically do not consider the effect of the time dynamics of operations and controls. Here, we use an optimal energy storage control algorithm to develop a heuristic procedure for energy storage placement and sizing. We generate many instances of intermittent generation time profiles and allow the control algorithm access to unlimited amounts of storage, both energy and power, at all nodes. Based on the activity of the storage at each node, we restrict the number of storage node in a staged procedure seeking the minimum number of storage nodes and total network storage that can still mitigate the effects of renewable fluctuations on network constraints. The quality of the heuristic is explored by comparing our results to seemingly "intuitive" placements of storage.