本文提出不确定性边际电价(UMP)用于定价不确定性和备用容量,结合鲁棒机组启停机制,解决可再生能源渗透带来的不确定性问题,通过仿真验证新概念和清算机制的有效性。

摘要:

近年来,可再生能源的渗透率增加导致电力系统不确定性加大,需通过灵活资源(即向上和向下发电备用)来应对。本文提出一种新概念——不确定性边际价格(UMP),用于对不确定性和备用进行定价,同时能量按区域边际价格(LMP)定价。本文提出了一种新的市场清算机制,以在日前市场中对发电和备用进行信用,对负载和不确定性进行收费,结合鲁棒机组启停(RUC)。在鲁棒优化框架下推导出UMP和LMP。UMP有助于将发电备用成本分配给不确定性来源。证明所提出的市场清算机制导致部分市场均衡。发现除了发电备用外,还需显式保留传输备用以应对不确定性。证明传输备用用于爬坡交付可能导致现有市场中的财务传输权利(FTR)资金不足。FTR资金不足可通过在所提市场清算机制中收集的拥堵基金来弥补。在六节点系统和IEEE 118节点系统上进行了仿真以验证新概念和市场清算机制。

英文摘要:

The increasing penetration of renewable energy in recent years has led to more uncertainties in power systems. These uncertainties have to be accommodated by flexible re- sources (i.e. upward and downward generation reserves). In this paper, a novel concept, Uncertainty Marginal Price (UMP), is proposed to price both the uncertainty and reserve. At the same time, the energy is priced at Locational Marginal Price (LMP). A novel market clearing mechanism is proposed to credit the gener- ation and reserve and to charge the load and uncertainty within the Robust Unit Commitment (RUC) in the Day-ahead market. We derive the UMPs and LMPs in the robust optimization framework. UMP helps allocate the cost of generation reserves to uncertainty sources. We prove that the proposed market clearing mechanism leads to partial market equilibrium. We find that transmission reserves must be kept explicitly in addition to generation reserves for uncertainty accommodation. We prove that transmission reserves for ramping delivery may lead to Financial Transmission Right (FTR) underfunding in existing markets. The FTR underfunding can be covered by congestion fund collected from uncertainty payment in the proposed market clearing mechanism. Simulations on a six-bus system and the IEEE 118-bus system are performed to illustrate the new concepts and the market clearing mechanism.