基于蒙特卡洛采样的互联队列导致的拥堵价格不确定性
Congestion Price Uncertainty From Interconnection Queue by Monte Carlo Sampling
AI总结:
本文针对发电互联队列导致的电网拥堵价格不确定性问题,提出用蒙特卡洛采样替代传统单点估计,在2000节点网络上验证了该方法的有效性,可得到更稳健的拥堵分布估计,适用于发电和大负荷项目规划。
摘要:
发电项目互联队列在项目规划时间尺度上给电网拥堵价格估计带来了离散不确定性。传统处理该不确定性的方法是对互联发电单元的少数最可能配置做出有根据的猜测。本文表明,蒙特卡洛采样是更有效的替代方案。在给定发电单元互联联合概率分布估计的情况下,少量样本即可得到良好的拥堵分布估计。关键在于,该问题并非关于罕见事件,而是关于一年中最恶劣时段的预期拥堵,这使得拥堵在互联事件分布中是常见结果。我们在一个2000节点的网络上给出了实证结果,对八种不同负荷场景下的安全约束直流最优潮流(security-constrained DCOPF)的价格结果取平均。对于网络的每条线路和事故情况,我们估计了完整分布以及平均价格和超过价格阈值的概率。单点估计不可靠,可能会误导关于线路是否可能拥堵的判断。结合前k个概率配置可得到改进的估计;然而,从分布中采样相同数量的样本会得到更稳健且精度相近的结果,还能得到误差估计。在分布模型中纳入相关性会带来微小变化,表明标准伯努利分布在大多数情况下已足够。该采样方法也适用于大负荷互联,应能为发电和大负荷项目的规划提供参考。
英文摘要:
The generation interconnection queue adds discrete uncertainty to power grid congestion price estimates on the project planning timescale. The conventional approach to this uncertainty is to make an informed guess of the single or few most likely configurations of generators that interconnect. In this paper, we show that Monte Carlo sampling is a more effective alternative. Given an estimate of the joint probability distribution of generator interconnections, a small number of samples yields good estimates of the congestion distribution. Crucially, this problem is not about rare events, but rather about the expected congestion over the worst times of the year, which makes congestion a common outcome over the distribution of interconnection events. We give empirical results on a 2000-bus network, averaging price outcomes from security-constrained DCOPF over eight different loading scenarios. For each line and contingency of the network, we estimate the full distribution as well as mean price and probability of exceeding a price threshold. Single-point estimates are unreliable and can be misleading about whether a line is likely to be congested. Combining the top k probability configurations yields improved estimates; however, sampling the same number from a distribution gives a more robust result of similar accuracy, as well as error estimates. Including correlation in the distribution model introduces small changes, showing that standard Bernoulli distributions suffice in most cases. The sampling approach is also applicable to large-load interconnection and should be of interest for planning both generation and large-load projects.
机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。