面向主动配电网的鲁棒性无功优化与电压控制方法:双时间尺度协调

Robust Reactive Power Optimization and Voltage Control Method for Active Distribution Networks via Dual Time-scale Coordination

Department of Electrical Engineering, Tsinghua University(清华大学电机工程系)

Weiye Zheng, Wenchuan Wu, Boming Zhang, Yongjie Wang

AI总结:

本文提出双时间尺度协调方法,通过鲁棒优化模型保障电压安全,结合确定性模型和列生成算法解决无功优化问题,验证了在不确定性条件下方法的有效性。

摘要:

在配电网络中,存在用于电压-无功调节的慢控设备和快控设备。这些慢控设备如电容器或电压调节器无法频繁操作,需提前数分钟调度(以下简称慢控)。由于负荷和分布式发电的不确定性,仅靠快控设备无法消除电压违规,尤其当慢控调度不当。本文提出双时间尺度协调的电压-无功控制方案,对应慢控和快控。在慢控中,开发了一个鲁棒电压和无功优化模型,确保在不确定参数变化在预定义范围内时,后续快控可维持系统电压安全。该非凸优化问题被松弛为混合整数二次锥问题,并推导了其子问题的对偶形式。然后使用列和约束生成算法求解鲁棒凸化模型。传统确定性优化模型用于确定快控机制。在实际中国配电线路、平衡IEEE 69节点和不平衡123节点基准配电网络上进行了数值测试。仿真结果表明,确定性模型不总是可行,电压违规可能发生。鲁棒模型在不确定性集的所有可能场景中均有效,且对网络损耗妥协很小。

英文摘要:

In distribution networks, there are slow controlling devices and fast controlling devices for Volt-VAR regulation. These slow controlling devices, such as capacitors or voltage regulators, cannot be operated frequently and should be scheduled tens of minutes ahead (Hereafter named as slow control). Since of the uncertainties in predicting the load and distributed generation, the voltage violations cannot be eliminated by fast controlling devices with improper schedule of the slow controlling devices. In this paper we propose dual time-scale coordination for the Volt-VAR control scheme, corresponding to slow and fast control. In the case of slow control, a robust voltage and reactive power optimization model is developed. This guarantees that subsequent fast controls can maintain the system's voltage security if the uncertain parameters vary within predefined limits. This nonconvex optimization problem is relaxed to a mix integer second order conic problem, and the dual form of its sub-problem is also derived. Then a column-and-constraint generation algorithm was used to solve the robust convexified model. A conventional deterministic optimization model can be used to determine the fast control mechanism. Numerical tests were conducted on a real distribution feeder in China, a balanced IEEE 69-bus and unbalanced 123-bus benchmark distribution networks. The simulation results show that solving the deterministic model is not always feasible and voltage violation may occur. The robust model was shown to be effective with respect to all possible scenarios in the uncertainty set, with little compromise in terms of network losses.