具有通信延迟的近线性时间排序问题
Scheduling with Communication Delay in Near-Linear Time
摘要:
研究了具有一致通信时延的一组相同机器上带优先约束工件的有效调度问题。这种优先约束的作业可以建模为有向非循环图,$G = (V, E)$。在此设置中,如果在不同的计算机上调度了两个优先级约束作业$u$和$v$(其中$v$依赖于$u$($u \prec v$)),则$v$必须在$u$完成后至少启动$ρ$时间单位。调度的目标是最小化完工时间,即从第一个工件开始到最后一个工件完成的总时间。本文的重点是提供一个有效的近似算法与近线性运行时间。我们建立在Lepere和Rapine [STACS 2002]的算法上,给出了一个在$\tilde{O}(|V| + |E|)$时间内运行的$O\left(\frac{\ln ρ}{\ln \ln ρ} \right)$近似算法。
英文摘要:
We consider the problem of efficiently scheduling jobs with precedence constraints on a set of identical machines in the presence of a uniform communication delay. Such precedence-constrained jobs can be modeled as a directed acyclic graph, $G = (V, E)$. In this setting, if two precedence-constrained jobs $u$ and $v$, with $v$ dependent on $u$ ($u \prec v$), are scheduled on different machines, then $v$ must start at least $ρ$ time units after $u$ completes. The scheduling objective is to minimize makespan, i.e. the total time from when the first job starts to when the last job finishes. The focus of this paper is to provide an efficient approximation algorithm with near-linear running time. We build on the algorithm of Lepere and Rapine [STACS 2002] for this problem to give an $O\left(\frac{\ln ρ}{\ln \ln ρ} \right)$-approximation algorithm that runs in $\tilde{O}(|V| + |E|)$ time.
机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。