一个100兆瓦级AI集群的供应到运行时优化
Provisioning to Runtime Optimization of a 100 MW-Scale AI Cluster
AI总结:
本文首次描述了超大规模AI数据中心从早期电力规划到运行时动态功耗管理的端到端过程,并提供了150兆瓦数据中心中83K GB200 GPU集群的详细功耗测量数据。
摘要:
AI数据中心的电力供应现在已成为迈向通用人工智能的最大瓶颈,甚至超过了AI加速器可用性的限制。据我们所知,本文首次描述了超大规模AI数据中心的端到端功耗管理过程;从提前6-12个月为下一代加速器进行早期电力规划,到大规模部署后调整功耗设置,最后到针对不断变化的工作负载进行动态运行时功耗管理。我们展示了一个容纳83K GB200 GPU集群的150兆瓦数据中心的详细功耗测量数据。我们分享了构建这一最先进AI集群的经验。我们希望这项工作能鼓励行业内的从业者分享他们自己的经验。
英文摘要:
The electric power supply for AI data centers is now the most significant bottleneck in the race toward Artificial General Intelligence, surpassing even the constraint of AI accelerator availability. To our knowledge, this paper is the first to describe the end-to-end power management process for a hyper-scale AI datacenter; from early power planning to accommodate next-generation accelerators 6--12 months before their general availability, to tuning power settings after large scale deployment, and finally to dynamic, runtime power management for evolving workloads. We present detailed power measurements for a 150 MW datacenter hosting a cluster of 83K GB200 GPUs. We share insights from building this state-of-the-art AI cluster. We hope this work encourages practitioners across the industry to share their own experiences as well.
机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。