面向灵活性的高效规划发起数据中心选址框架

Flexibility-Aware Framework for Efficient Planner-Initiated Siting of Data Center

Texas A&M University(德克萨斯农工大学);Harvard University(哈佛大学)

Dongjoo Kim, Lin Dong, Le Xie

AI总结:

本文提出一种整合可靠性筛选、市场影响评估和多准则评分的框架,通过提升灵活性扩大数据中心选址范围,缩短项目周期,同时保持电网可靠性和市场稳定性。

摘要:

能源密集型AI数据中心的爆炸性增长正超越电力电网互联和传输扩展的速度。尽管运营灵活性被提出以缓解这种压力,但现有流程通常是反应性的,仅在项目进入多year互联队列后才评估。为此,我们引入一种规划发起的选址框架,整合(i)可靠性门控筛选,(ii)基于标准化灵活性包络(固定、暂停和转移)的系统级市场影响评估,以及(iii)熵权多准则评分,以生成排名的预认证互联准备地点目录。应用于合成的2000节点得克萨斯电力系统,该框架证明,运营灵活性在1 GW和2 GW规模下分别将选址前沿扩大9-17%和19-21%,中位数每小时平均价格基本不变(2 GW情况为24.32美元/MWh),转移包络通过约3.4%减少高峰小时价格波动,同时在非高峰小时有最小副作用。利用预认证包络以绕过主要传输增强,该工作流程使首次通电时间缩短12-18个月,比传统5-8年项目主导流程保守减少3.5-4年。这种技术无关框架为系统运营商和监管机构提供了一种主动决策工具,以加快大型灵活负载的部署,同时保持电网可靠性和市场稳定性。

英文摘要:

Explosive growth in energy-intensive AI data centers is outstripping the pace of power grid interconnection and transmission expansion. While operational flexibility has been proposed to mitigate this stress, existing processes are often reactive and evaluate projects only after they enter a multi-year interconnection queue. To address this, we introduce a planner-initiated siting framework that integrates (i) reliability-gated screening, (ii) system-wide market-impact assessment under standardized flexibility envelopes (firm, pause, and shift), and (iii) entropy-weighted multi-criteria scoring to produce ranked, pre-certified catalogues of interconnection-ready locations. Applied to a synthetic 2,000-bus Texas power system, the framework demonstrates that operational flexibility expands the siting frontier by 9-17% at 1 GW and 19-21% at 2 GW compared to firm operation. Median all-hour average prices remain essentially unchanged (USD 24.32/MWh for the 2 GW cases), and the shift envelope attenuates peak-hour price dispersion by approximately 3.4% with minimal side effects during off-peak hours. Utilizing pre-certified envelopes to bypass major transmission reinforcements, this workflow enables first energization in 12-18 months, a conservative reduction of 3.5-4 years versus the conventional 5-8 year project-led process. This technology-agnostic framework provides a proactive decision-making tool for system operators and regulators to fast-track large flexible loads while preserving grid reliability and market stability.

机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。

↑