关于通过精确延迟调度耦合任务以最小化最大延迟的研究

On scheduling coupled tasks with exact delays to minimize maximum lateness

Memorial University(纪念大学)

Wiesław Kubiak

AI总结:

本文提出多项式时间算法解决耦合任务调度问题,通过精确延迟最小化最大延迟,区分可兼容与不可兼容两种情况。

摘要:

本文研究了通过精确延迟调度耦合任务以最小化最大延迟的问题。第一个任务的处理时间为 $p>0$,第二个任务的处理时间为 $b_i\geq 0$,且第二个任务必须在第一个任务完成后的恰好 $p$ 个时间单位后开始。耦合任务有截止时间 $d_i$。这些任务在单一机器上进行调度以最小化最大延迟。文献中该问题尚未解决,几乎没有关于通过精确延迟调度耦合任务以最小化最大延迟的结论。本文为可兼容($d_i\geq d_j$ 时 $b_i\geq b_j$)和不可兼容($d_i\geq d_j$ 时 $b_i\leq b_j$)的情况提供了多项式时间算法。一般问题的复杂性仍保持开放。

英文摘要:

This paper studies scheduling coupled tasks with exact delays to minimize maximum lateness. The first task has processing time $p>0$ and the second $b_i\geq 0$, also the second needs to start exactly $p$ units of time after the completion of the first. The couple has due date $d_i$. The tasks are scheduled on a single machine to minimize maximum lateness. The problem has been left open in the literature which offer hardly any results on scheduling coupled tasks with exact delays to minimize maximum lateness. The paper shows polynomial time algorithms for \emph{agreeable} ($d_i\geq d_j$ implies $b_i\geq b_j$) and \emph{disagreeable} ($d_i\geq d_j$ implies $b_i\leq b_j$) cases. The complexity of the general problem remains open.

机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。

↑