地面望远镜阵列开发的项目管理

Project Management for Ground-based Telescope Array Development

Ji Hoon Kim, Myungshin Im, Hyung Mok Lee, Seo-Won Chang

AI总结:

本研究介绍首尔国立大学7DT地面望远镜阵列的设施配置、数据规模、存储计算及远程运行方案,重点分享低预算学术环境下该项目在人力、风险、财务应急等方面的管理经验。

摘要:

首尔国立大学引力波宇宙中心自2023年10月起运行其主要观测设施——7维望远镜(7-Dimensional Telescope,7DT)。7DT位于智利里奥乌尔塔多山谷的埃尔绍塞天文台,由20台50厘米口径望远镜组成,配备40个半峰全宽为25 nm的中带滤光片,以及一台6100万像素的CMOS相机。\n7DT每晚产生约1 TB的光谱映射图像数据(含校准数据);待我们计划的三层巡天项目——参考成像巡天(Reference Imaging Survey)、广域巡天(Wide Field Survey)和深度监测巡天(Intensive Monitoring Survey)——于2024年启动后,还会产出数据处理流水线的副产品。我们预计原始数据、处理后数据及数据产品(如校准叠加图像、光谱立方体和天体星表)合计每年将产生1 PB的数据量。\n为容纳如此海量的数据,我们目前已建成1 PB的数据存储系统,并将以每年1 PB的速度扩容。我们还配备了搭载2张NVIDIA A100 GPU卡的高性能计算设施,因为我们计划对引力波事件的后续观测数据开展实时数据处理与分析。为支撑这一需求,我们在韩国与智利的设施之间建立了400 Mbps的网络连接。依托这一高性能网络,我们自2023年10月起实现了完全远程运行。\n在本次报告中,我们将介绍地面望远镜设施项目设计、规划与实施的细节,尤其聚焦低预算学术环境下的项目推进。在尽可能全面覆盖各方面内容的同时,我们将重点阐述人力资源管理、项目风险管理和财务应急管理。

英文摘要:

Center for the Gravitational-Wave Universe at Seoul National University has been operating its main observational facility, the 7-Dimensional Telescope (7DT) since October 2023. Located at El Sauce Observatory in Chilean Rio Hurtado Valley, 7DT consists of 20 50-cm telescopes equipped with 40 medium-band filters of 25 nm full width at half maximum along with a CMOS camera of 61 megapixels. 7DT produces about 1 TB per night of spectral mapping image data including calibration, and the byproduct of the data reduction pipeline once our planned three layered surveys (Reference Imaging Survey, Wide Field Survey, and Intensive Monitoring Survey) start in 2024. We are expecting to generate 1 PB per year by combining raw data, reduced data, and data products (e.g. calibrated stacked images, spectral cubes, and object catalogs). To incorporate this huge amount of data, we now have a data storage for 1 PB which we will increment by 1 PB per year. We also have a high-performance computation facility that is equipped with 2 NVIDIA A100 GPU cards since we plan to carry out real-time data reduction and analysis for follow-up observation data of gravitational wave events. To incorporate this, we established a 400 Mbps network connection between the facilities in Korea and Chile. Taking advantage of the high-performance network, we have been carrying out fully remote operations since October 2023. In this talk, we present details of designing, planning, and executing the ground-based telescope facility project, especially within low-budget academic environments. While we cover as much ground as possible, we will emphasize human resource management, project risk management, and financial contingency management.

机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。

↑