超越项目风险管理中的概率-影响矩阵:一种用于风险优先级排序的定量方法
Beyond probability-impact matrices in project risk management: A quantitative methodology for risk prioritisation
AI总结:
本文提出一种基于蒙特卡洛模拟和MCSimulRisk软件的定量方法,用于克服传统风险矩阵的局限,实现对项目风险按持续时间和成本目标的独立优先级排序。
摘要:
处理风险管理的项目经理经常面临一项艰巨的任务,即确定影响项目的各种风险源的相对重要性。这种优先级排序对于引导管理工作以确保更高的项目盈利能力至关重要。风险矩阵是学术界和各行业从业者广泛认可的工具,用于根据风险发生的可能性及其对项目目标的影响来评估和排列风险。然而,现有文献强调了使用风险矩阵的若干局限性。针对其使用中的弱点,本文提出了一种对项目风险进行优先级排序的新方法。使用蒙特卡洛模拟(MCS)通过模拟软件 MCSimulRisk 对风险进行定量优先级排序。除了定义项目活动外,模拟还通过建模已识别风险的概率及其对成本和持续时间的影响来纳入这些风险。通过这种新方法,提供了对每种风险影响的定量评估,衡量标准是其对项目持续时间和总成本的影响。这使得能够根据风险对项目持续时间的影响来区分关键风险,如果将成本作为优先目标,这种影响可能会有所不同。该提案对项目经理很有意义,因为一方面,他们将了解每种风险对项目持续时间和成本目标的绝对影响,另一方面,能够独立区分每种风险对持续时间目标和成本目标的影响。
英文摘要:
The project managers who deal with risk management are often faced with the difficult task of determining the relative importance of the various sources of risk that affect the project. This prioritisation is crucial to direct management efforts to ensure higher project profitability. Risk matrices are widely recognised tools by academics and practitioners in various sectors to assess and rank risks according to their likelihood of occurrence and impact on project objectives. However, the existing literature highlights several limitations to use the risk matrix. In response to the weaknesses of its use, this paper proposes a novel approach for prioritising project risks. Monte Carlo Simulation (MCS) is used to perform a quantitative prioritisation of risks with the simulation software MCSimulRisk. Together with the definition of project activities, the simulation includes the identified risks by modelling their probability and impact on cost and duration. With this novel methodology, a quantitative assessment of the impact of each risk is provided, as measured by the effect that it would have on project duration and its total cost. This allows the differentiation of critical risks according to their impact on project duration, which may differ if cost is taken as a priority objective. This proposal is interesting for project managers because they will, on the one hand, know the absolute impact of each risk on their project duration and cost objectives and, on the other hand, be able to discriminate the impacts of each risk independently on the duration objective and the cost objective.
机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。