项目进度计划中标度的涌现
Emerge of scaling in project schedules
AI总结:
本文发现建筑项目活动持续时间与总浮动时间呈幂律标度,证明持续时间标度是延误分布估计的关键,并为参考类别预测提供数学形式。
摘要:
项目进度计划包含一个活动网络、活动持续时间、每项活动的最早和最晚完成日期,以及相关的总浮动时间或松弛时间,即最晚日期与最早日期之差。本文表明,建筑项目进度计划中的活动持续时间和总浮动时间分布呈现出幂律标度。活动持续时间的幂律标度可由专业化的历史过程解释:该过程将旧活动碎片化,形成持续时间更短的新活动。相比之下,各活动间总浮动时间分布的幂律标度由活动网络决定。本文证明,活动持续时间分布的幂律标度对于良好估计项目延误分布至关重要,而实际总浮动时间分布的相关性较低。最后,利用极值理论和标度论证,本文针对项目延误分布的参考类别预测给出了数学证明。项目延误累积分布函数为 $G(z) = \exp( - (z_c/z)^{1/s})$,其中 $s>0$ 和 $z_c>0$ 分别为形状参数和尺度参数。此外,若活动延误服从经验数据所表明的对数正态分布,则 $s=1$ 且 $z_c \sim N^{0.20}d_{\max}^{1+0.20(1-γ_d)}$,其中 $N$ 为活动数量,$d_{\max}$ 为以天为单位的最大活动持续时间,$γ_d$ 为活动持续时间分布的幂律指数。这些结果为项目进度计划、参考类别预测和延误风险分析提供了新的见解。
英文摘要:
A project schedule contains a network of activities, the activity durations, the early and late finish dates for each activity, and the associated total float or slack times, the difference between the late and early dates. Here I show that the distribution of activity durations and total floats of construction project schedules exhibit a power law scaling. The power law scaling of the activity durations is explained by a historical process of specialization fragmenting old activities into new activities with shorter duration. In contrast, the power law scaling of the total floats distribution across activities is determined by the activity network. I demonstrate that the power law scaling of the activity duration distribution is essential to obtain a good estimate of the project delay distribution, while the actual total float distribution is less relevant. Finally, using extreme value theory and scaling arguments, I provide a mathematical proof for reference class forecasting for the project delay distribution. The project delay cumulative distribution function is $G(z) = \exp( - (z_c/z)^{1/s})$, where $s>0$ and $z_c>0$ are shape and scale parameters. Furthermore, if activity delays follow a lognormal distribution, as the empirical data suggests, then $s=1$ and $z_c \sim N^{0.20}d_{\max}^{1+0.20(1-γ_d)}$, where $N$ is the number of activities, $d_{\max}$ the maximum activity duration in units of days and $γ_d$ the power law exponent of the activity duration distribution. These results offer new insights about project schedules, reference class forecasting and delay risk analysis.
机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。