计算时间可调的多阶段作业机器-运输工具联合调度
Joint Machine-Transporter Scheduling for Multistage Jobs with Adjustable Computation Time
AI总结:
针对多阶段作业中机器与续航受限机器人的联合调度问题,提出时间离散化、作业聚类与滑动窗口整数线性规划方法,可在最优性与计算时间间权衡。
摘要:
本文针对一类联合问题提出了一种计算时间可调的可扩展解决方案,该问题涉及为必须按照固定工序顺序跨多个阶段完成的任务调度和分配机器与运输工具。系统采用具有最大行驶里程的电池驱动多机器人系统作为阶段之间的运输工具,并将充电视为一道工序。机器人在单个作业完成前只被分配给该作业。此外,假设工序完成时间取决于机器和工序类型,但与作业无关。本研究旨在最小化一个加权多目标,该目标同时包含运输工具所需时间和所消耗能量。该问题是带运输的柔性流水车间问题的一种变体,已被证明是 NP 完全的。为提供解决方案,本文对时间进行离散化,按时间划分解空间,并将作业聚类为不同的组。最后,在滑动时间窗口内应用整数线性规划求解器来确定分配并生成调度,以最小化目标函数。计算时间可根据每个分段中选择的作业数量而减少,但需在最优性上进行权衡。所提出的算法应用于一个水样采集项目,其中水样采集作业被分配给机器人,实验室的样本交付得到调度,并且机器人被路线规划至充电站。
英文摘要:
This paper presents a scalable solution with adjustable computation time for the joint problem of scheduling and assigning machines and transporters for missions that must be completed in a fixed order of operations across multiple stages. A battery-operated multi-robot system with a maximum travel range is employed as the transporter between stages and charging them is considered as an operation. Robots are assigned to a single job until its completion. Additionally, The operation completion time is assumed to be dependent on the machine and the type of operation, but independent of the job. This work aims to minimize a weighted multi-objective goal that includes both the required time and energy consumed by the transporters. This problem is a variation of the flexible flow shop with transports, that is proven to be NP-complete. To provide a solution, time is discretized, the solution space is divided temporally, and jobs are clustered into diverse groups. Finally, an integer linear programming solver is applied within a sliding time window to determine assignments and create a schedule that minimizes the objective. The computation time can be reduced depending on the number of jobs selected at each segment, with a trade-off on optimality. The proposed algorithm finds its application in a water sampling project, where water sampling jobs are assigned to robots, sample deliveries at laboratories are scheduled, and the robots are routed to charging stations.
机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。