一种考虑电缆布线的大规模陆上风电场选址高效求解器

An efficient solver for large-scale onshore wind farm siting including cable routing

Jaap Pedersen, Jann Michael Weinand, Chloi Syranidou, Daniel Rehfeldt

AI总结:

针对陆上风电场选址与电网集成规划的不足,提出基于配额Steiner树的布局与电缆布线集成精确求解方法,性能优于通用MIP求解器,验证了同步优化电网接入的必要性,可辅助大区域风电场规划决策。

摘要:

现有的陆上风电场选址与电网接入规划方法往往无法得到最低成本方案,也难以兼顾社会与环境考量。本文针对陆上风电场规划中的布局与电缆布线集成问题,基于配额Steiner树问题提出了一种精确求解方法。通过对已知的有向割公式进行新颖变换,结合约简技术与启发式算法,我们设计出一款精确求解器,可求解大规模问题实例,且性能优于通用MIP求解器。我们在德国选定区域开展研究,分析了陆上风电场选址在成本最小化与景观影响之间的权衡关系。案例研究显示,成本与景观影响这两个目标标准之间存在显著权衡,但对其中一项标准施加小幅约束,就能大幅改善另一项标准的表现。此外,本文证明,与许多仅关注风机选址的方法不同,电网接入必须同步优化,才能避免风电场项目过程中出现成本过高或景观影响过大的问题。我们提出的新型问题公式与开发的求解器可辅助规划人员决策,未来可用于大区域范围内的风电场优化。

英文摘要:

Existing planning approaches for onshore wind farm siting and grid integration often do not meet minimum cost solutions or social and environmental considerations. In this paper, we develop an exact approach for the integrated layout and cable routing problem of onshore wind farm planning using the Quota Steiner tree problem. Applying a novel transformation on a known directed cut formulation, reduction techniques, and heuristics, we design an exact solver that makes large problem instances solvable and outperforms generic MIP solvers. In selected regions of Germany, the trade-offs between minimizing costs and landscape impact of onshore wind farm siting are investigated. Although our case studies show large trade-offs between the objective criteria of cost and landscape impact, small burdens on one criterion can significantly improve the other criteria. In addition, we demonstrate that contrary to many approaches for exclusive turbine siting, grid integration must be simultaneously optimized to avoid excessive costs or landscape impacts in the course of a wind farm project. Our novel problem formulation and the developed solver can assist planners in decision-making and help optimize wind farms in large regions in the future.

机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。

↑