IT项目成本超支的实证现实:发现幂律分布
The Empirical Reality of IT Project Cost Overruns: Discovering A Power-Law Distribution
摘要:
如果管理人员假设信息技术(IT)项目成本超支的正态分布或接近正态分布,并且成本超支可以显示为遵循幂律分布,则管理人员可能会因严重低估大成本超支的可能性而无意中将其组织暴露于极端风险。在本研究中,我们收集并分析了由5,392个IT项目组成的大样本,以实证检验IT项目成本超支的概率分布。此外,我们提出并研究了一种机制,可以解释这样的分布。我们的研究结果表明,IT项目的成本风险远远高于决策者和学者通常所假设的。具体来说,我们发现,IT项目成本超支遵循幂律分布,其中有大量的项目相对较小的超支和一个胖尾巴,其中包括一个极端超支的项目数量较少。一个可能的生成机制,确定的幂律分布被发现在IT系统中的技术组件之间的相互依赖性。我们提出并证明,通过计算机模拟,在一个单一的技术组件的问题可能会导致链式反应中,其他相互依赖的组件受到影响,造成大量的超支。幂律告诉我们的是,极端的IT项目成本超支将会发生,如果管理人员假设超支遵循正态或接近正态分布,那么这些超支的普遍性将被严重低估。这突出表明了预先实际评估和降低新IT项目成本风险的重要性。
英文摘要:
If managers assume a normal or near-normal distribution of Information Technology (IT) project cost overruns, as is common, and cost overruns can be shown to follow a power-law distribution, managers may be unwittingly exposing their organizations to extreme risk by severely underestimating the probability of large cost overruns. In this research, we collect and analyze a large sample comprised of 5,392 IT projects to empirically examine the probability distribution of IT project cost overruns. Further, we propose and examine a mechanism that can explain such a distribution. Our results reveal that IT projects are far riskier in terms of cost than normally assumed by decision makers and scholars. Specifically, we found that IT project cost overruns follow a power-law distribution in which there are a large number of projects with relatively small overruns and a fat tail that includes a smaller number of projects with extreme overruns. A possible generative mechanism for the identified power-law distribution is found in interdependencies among technological components in IT systems. We propose and demonstrate, through computer simulation, that a problem in a single technological component can lead to chain reactions in which other interdependent components are affected, causing substantial overruns. What the power law tells us is that extreme IT project cost overruns will occur and that the prevalence of these will be grossly underestimated if managers assume that overruns follow a normal or near-normal distribution. This underscores the importance of realistically assessing and mitigating the cost risk of new IT projects up front.
机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。