基于混合仿真的RCC路面项目资源规划与可施工性分析
Hybrid Simulation-based Resource Planning and Constructability Analysis of RCC Pavement Projects
摘要:
基础设施建设的关键挑战之一是设计和规划业务及其相关资源。影响资源生产力的不同因素和变量的复杂的相互关联的组合,使模拟成为业务规划的一种强有力的方法。最近,建筑部门在应用各种模拟工具以进一步提高项目规划质量方面出现了显著的激增,特别是在大型基础设施开发方面(例如,公路建设)。由于资源配置不当可能导致成本超支,因此优化大型项目(如大型路面项目)的设计和施工规划阶段至关重要。最近的研究旨在通过结合各种模拟方法(例如,离散事件仿真、系统动力学、基于代理的仿真和混合仿真),以增强规划阶段。本文介绍了一种不断发展的实时混合仿真技术,考虑项目的内在时变输入和因素,以优化碾压混凝土(RCC)路面项目的规划。几个方案进行了调查,使用各种资源组合,以实现最佳的执行方法交付混凝土的项目。一个实际的高速公路项目案例研究验证了所提出的模型及其应用,为未来的项目。研究结果表明,基于仿真的方法在碾压混凝土路面项目资源规划中的有效性。
英文摘要:
One of the critical challenges in infrastructural constructions is designing and planning operations and their related resources. The complex interlinked composition of different factors and variables affecting resource productivity has made simulation a powerful approach for operational planning. The construction sector has recently seen a notable surge in applying various simulation tools to enhance further the quality of projects planning, particularly in large-scale infrastructure developments (e.g., highway construction). Due to possible cost overruns in improper resource allocation, optimizing the design and construction planning stages of megaprojects such as massive pavement projects is essential. Recent studies aimed to build a simulation-based strategy in construction designing and planning by combining various simulation approaches (e.g., discrete-event simulation, system dynamics, agent-based simulation, and hybrid simulation) to enhance the planning phase. This paper introduces an evolving real-time hybrid simulation technique regarding the projects intrinsic time-varying inputs and factors to optimize the planning of Roller Compacted Concrete (RCC) pavement projects. Several scenarios are investigated using various resource combinations to achieve the best execution method for delivering concrete to the project. An actual highway project case study validates the proposed model and its application for future projects. This studys findings exhibit the proficiencies of the simulation-based approach in resource planning of RCC pavement projects within the time and cost constraints and their related regulations.
机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。