软件开发工作量估计偏差的度量:避免估计偏差的有偏度量
Measurement of software development effort estimation bias: Avoiding biased measures of estimation bias
摘要:
在本文中,我们提出了改进如何估计偏差,例如,测量低估努力的趋势。所提议的办法强调需要知道估计数的含义,即,我们评估的估计类型,以及给定的估计类型与使用的偏差度量之间匹配的必要性。我们表明,即使完美的估计的平均努力不会导致零估计偏差的期望时,经常使用的偏见措施:(实际努力-估计的努力)/实际努力。这种措施反而会奖励低估平均努力的人。我们还提供了偏置措施,匹配的平均值和中位数的努力估计的例子,并认为,有,在一般情况下,没有实际的偏置措施的估计最有可能的努力。本文的结论与软件开发工作量估计的偏差评估的影响。
英文摘要:
In this paper, we propose improvements in how estimation bias, e.g., the tendency towards under-estimating the effort, is measured. The proposed approach emphasizes the need to know what the estimates are meant to represent, i.e., the type of estimate we evaluate and the need for a match between the type of estimate given and the bias measure used. We show that even perfect estimates of the mean effort will not lead to an expectation of zero estimation bias when applying the frequently used bias measure: (actual effort - estimated effort)/actual effort. This measure will instead reward under-estimates of the mean effort. We also provide examples of bias measures that match estimates of the mean and the median effort, and argue that there are, in general, no practical bias measures for estimates of the most likely effort. The paper concludes with implications for the evaluation of bias of software development effort estimates.
机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。