The CESAW dataset: a conversation

Derek M. Jones, William R. Nichols

摘要:

通过数据分析师与收集、编译和最初分析数据的人员之间的对话,对使用Team Software Process实现的45个项目的开发人员执行的61,817项任务进行了分析。五个项目是安全关键项目,共涉及28 899项任务。使用工作分解结构将项目分解,以创建分层组织,任务位于叶节点。WBS信息使得能够调查项目内的任务组织,例如,相关任务如何排序在一起。任务数据包括:任务类型,匿名开发者ID,开始/结束时间/日期,以及中断和休息时间;总共203,621个时间事实。任务努力估计的准确性被认为是影响因素,如作出估计的人,所涉及的项目,并倾向于使用整数。

英文摘要:

An analysis of the 61,817 tasks performed by developers working on 45 projects, implemented using Team Software Process, is documented via a conversation between a data analyst and the person who collected, compiled, and originally analyzed the data. Five projects were safety critical, containing a total of 28,899 tasks. Projects were broken down using a Work Breakdown Structure to create a hierarchical organization, with tasks at the leaf nodes. The WBS information enables task organization within a project to be investigated, e.g., how related tasks are sequenced together. Task data includes: kind of task, anonymous developer id, start/end time/date, as well as interruption and break times; a total of 203,621 time facts. Task effort estimation accuracy was found to be influenced by factors such as the person making the estimate, the project involved, and the propensity to use round numbers.

机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。

↑