简化边上活动图
Simplifying Activity-on-Edge Graphs
摘要:
我们形式化的简化活动的边缘图用于可视化项目进度表,其中的顶点的图形代表项目的里程碑,和边缘代表项目的任务或里程碑之间的时间约束。在这个框架中,项目的时间轴可以被构造为图的分层绘制,其中顶点的级别表示每个里程碑计划发生的时间。我们专注于以下问题:给定一个活动的边缘图代表一个项目,找到一个等效的活动的边缘图(一个具有相同的关键路线),具有最小可能数量的里程碑顶点之间的所有等效的活动的边缘图。我们提供了一个多项式时间算法来解决这个图最小化问题。
英文摘要:
We formalize the simplification of activity-on-edge graphs used for visualizing project schedules, where the vertices of the graphs represent project milestones, and the edges represent either tasks of the project or timing constraints between milestones. In this framework, a timeline of the project can be constructed as a leveled drawing of the graph, where the levels of the vertices represent the time at which each milestone is scheduled to happen. We focus on the following problem: given an activity-on-edge graph representing a project, find an equivalent activity-on-edge graph (one with the same critical paths) that has the minimum possible number of milestone vertices among all equivalent activity-on-edge graphs. We provide a polynomial-time algorithm for solving this graph minimization problem.
机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。