非均质预应力预制梁多周期生产计划问题的建模与求解方法

Heterogeneous Prestressed Precast Beams Multiperiod Production Planning Problem: Modeling and Solution Methods

Kennedy Araujo, Tiberius Bonates, Bruno Prata, Anselmo Pitombeira-Neto

摘要:

预应力预制梁是一种用牵引元件拉伸的梁。预应力预制梁工厂的一项常见任务是在一定时间范围内满足客户的需求。典型的订单包括不同长度和类型的梁,不同的梁可能需要不同的固化周期。我们把这种生产计划问题称为非均质预应力预制梁多周期生产计划问题。我们正式定义了HPPBMPP,认为它的NP-硬度,并介绍了四种新的整数规划模型的解决方案和规模缩减启发式(SRH)。我们提出了六个优先级规则来产生可行解。我们进行计算测试的一组合成实例,是基于数据从现实世界的情况下,并讨论了案例研究。我们的实验表明,模型可以最佳地解决小的实例,而SRH可以产生高质量的解决方案,为大多数情况下。

英文摘要:

A prestressed precast beam is a type of beam that is stretched with traction elements. A common task in a factory of prestressed precast beams involves fulfilling, within a time horizon, the demand ordered by clients. A typical order includes beams of different lengths and types, with distinct beams potentially requiring different curing periods. We refer to the problem of planning such production as Heterogeneous Prestressed Precast Beams Multiperiod Production Planning (HPPBMPP). We formally define the HPPBMPP, argue its NP-hardness, and introduce four novel integer programming models for its solution and a size reduction heuristic (SRH). We propose six priority rules to produce feasible solutions. We perform computational tests on a set of synthetic instances that are based on data from a real-world scenario and discuss a case study. Our experiments suggest that the models can optimally solve small instances, while the SRH can produce high-quality solutions for most instances.

机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。

↑