软件项目工期的概率估计

Probabilistic estimation of software project duration

Andy M. Connor

摘要:

本文提出了一个框架,在整个项目生命周期中使用的软件设计项目的估计表示的不确定性。该框架是灵活的,以适应在项目中的不确定性,并利用蒙特卡洛模拟计算传播的不确定性,努力估计对总项目的不确定性,因此,给项目经理的手段,使明智的决策在整个项目的生命。该框架还提供了一个机制,通过使用历史数据库积累项目知识,使工作量估计能够参考或实际上基于以前项目的成果。使用模拟数据的初步结果和进一步工作的途径进行了讨论。

英文摘要:

This paper presents a framework for the representation of uncertainty in the estimates for software design projects for use throughout the entire project lifecycle. The framework is flexible in order to accommodate uncertainty in the project and utilises Monte Carlo simulation to compute the propagation of uncertainty in effort estimates towards the total project uncertainty and therefore gives a project manager the means to make informed decisions throughout the project life. The framework also provides a mechanism for accumulating project knowledge through the use of a historical database, allowing effort estimates to be informed by, or indeed based upon, the outcome of previous projects. Initial results using simulated data are presented and avenues for further work are discussed.

机构、总结、中文摘要均由AI分析而来,可能存在错误,请以论文正文为准。

↑